2024 Pavement Management Program

Project Overview

The City of Burien is responsible for repairs and maintenance of approximately 137 centerline miles of paved roads (residential 78%, collector 13%, arterial 9%).

The annual pavement management program consists of pavement preservation applications (crack sealing, micro surfacing and slurry seal coatings), maintenance items (pothole repairs), together with necessary full reconstruction and rehabilitation pavement overlay projects. The purpose of the program is to reduce the overall long-term cost for maintaining the condition of Burien streets.

Each year projects are selected by reviewing the current pavement condition Index (PCI), field inspections, and resident input.

2024 Pavement Repairs and Overlay Projects

The City will be conducing necessary pavement repairs, pavement preservation, and improvements. The project will consist of pothole repairs, grind and overlay of new asphalt pavement, and ADA-compliant crosswalk improvements along school pedestrian corridors.

2024 Project Areas:

  • Site 1, Gregory Heights Neighborhood: 16th Ave SW (SW 168th St. to SW 160th St.)
  • Site 2, Downtown Neighborhood: SW 154th St (from 4th Ave SW to 2nd Ave SW)
  • Site 3, Beverly Park Neighborhood: S. 115th St (from 10th Ave S. to 12th Ave S.)

Project Status 

  • April-June 2024: Project Design
  • July-September 2024: Construction

Project Updates

The city will provide updates and notify those residents by mail who may be affected by construction and paving activities.

Project Manager

David Traub, Capital Projects Manager

(206) 241-4647

[email protected]

 

Updated June 20, 2024