Project Overview
The City of Burien is responsible for repairs and maintenance of approximately 137 centerline miles of paved roads (residential 78%, collector 13%, arterial 9%).
The annual Pavement Management Program consists of several preventive maintenance items, including pothole repairs, crack sealing, slurry seal coating, together with necessary full reconstruction and rehabilitation pavement overlay projects. The purpose of the program is to reduce the overall long-term cost for maintaining the condition of Burien streets.
Each year the maintenance selected and geographic location within the City’s Street network is determined by the current Pavement Condition Index (PCI), field inspections, and resident input.
2022 Pavement Repairs and Overlay Projects
The City will be conducting necessary pavement repairs and pavement improvements projects within the Boulevard Park neighborhood area consisting of reconstruction and rehabilitation, grind and overlay of new asphalt pavement, and ADA-compliant improvements along school and bus route corridors.
Above: Grind and overlay of new asphalt.
Pavement Overlay Streets
- 20th Ave S. ( from S. 128th St to S. 124th St)
- 21st Ave S. ( from S. 126th St to cul-de-sac)
- 22nd Ave S. ( from S. 128th St to S. 124th St)
- 23rd Ave S. ( from S. 128th St to S. 126th St)
- 24th Ave S. ( from S. 120th St to S. 116th St)
Project Status
- May–June 2022: Project Selection and Design
- June–July 2022: Advertise for Bids
- August–September 2022: Construction
Project Updates
The City will provide updates and notify those residents by mail who may be affected by construction and paving activities.
Project Manager
For information, please contact (206) 241-4647 or send an email to [email protected].
Updated May 27, 2022