Annex Demolition

The City of Burien is soliciting bids from qualified firms that provide building demolition services for the removal, disposal, clean up, site grading, and seeding for the Burien Community Center Annex (Annex) site, including the buildings located at 425 SW 144th St., Burien WA 98166. For questions about the project, please contact the project manager at ParksProjects@burienwa.gov.

Burien Community Center Annex Demolition July 8, 2020 Bid Results

View the July 8, 2020 Bid Results.

Mandatory Site Walk Outcomes

The following contractors attended a mandatory site walk on June 23, 2020 and are eligible to submit a response to the request for the Annex Demolition. View the Mandatory Site Walk Agenda for reference.

1. AEC 
2. Ascendent
3.  Bluelam
4.  CGI
5.  Liuna
6.  Rivers Edge
7.  Titan
8.  3 Kings 
9. Dickson Company

Clarifications:

  1. No bid bond is required.
  2. Final MENG Facility Condition Report of December 16, 2019 and Good Faith Survey testing conducted by AHERA accredited asbestos inspector Jacob Lindberg. Reports, testing, and findings prepared for Meng Analysis, by Terracon Consultants, Inc. for the City of Burien Community Center “Annex”. All testing and background related to the “Annex” can be found on the City of Burien website.
  3. All questions to be submitted to ParksProjects@burienwa.gov no later than July 1, 2020.
  4. No questions received.

Addenda

  • Addenda 1, dated July 2, 2020 including revised Bid Proposal Form.
  • Addenda 2, dated July 6, 2020

Timeline

The work is anticipated to be conducted between August 1, 2020 and September 30, 2020. There will be a mandatory pre-bid site walk, by appointment and following COVID-19 safety protocols, on June 23, 2020. Firms must deliver proposals prior to the public bid opening on July 8. Please review the following bid documents for further details.

 Bid Date/Time:  July 8, 2020 at 1:00 p.m.
 Bid Opening:  Burien Community Center at 14700 6th Ave SW, Burien, WA 98166
 Project Location:  425 SW 144th Street, Burien, WA 98166 
  
 Bid Schedule
 06/19/2020:  Project Advertised
 06/23/2020:  Mandatory Site Walk
 07/01/2020:  Inquiries Due
 07/06/2020:  Inquiry Responses Posted
  
 Preliminary Project Schedule
 07/13/2020:  Notification to Responsive Bidder
 07/24/2020:  Contract Execution
 07/24/2020:  Notice to Proceed
 07/27/2020:  Pre-Construction Meeting 
 08/01/2020:  Demolition Commencement
 09/30/2020:  Completion of Demolition 